The Station 51 construction
project remains under way as it enters its fifteenth month of on-site
construction. Many of the factors that slowed construction during the last
few months have all been corrected and contractors are entering the final phases
of their work. The interior is nearly complete with just touch-up and some
electrical finishes to be completed. Landscaping is scheduled to begin
next week after the final paving has been done. A final completion date
has not yet been set, but is expected to be set at the next construction team
meeting to be held next week.
|
Construction |
|
|
Front Elevation |
||
|
Rear Elevation |
||
|
Lower Level Plan |
||
![]() |
||
| Main Level Plan | ||
![]() |
||
| Upper Level Plan |
|
©1997-2011 White River Township Fire Department, Inc. - All rights reserved White River Township Fire Department maintains this site ("the Site") for your personal entertainment, information, education, and communication. Feel free to browse the Site, but please read the terms and conditions before doing so. |