August 1, 2007

Station 51 construction update 15

      The Station 51 construction project remains under way as it enters its fifteenth month of on-site construction.  Many of the factors that slowed construction during the last few months have all been corrected and contractors are entering the final phases of their work.  The interior is nearly complete with just touch-up and some electrical finishes to be completed.  Landscaping is scheduled to begin next week after the final paving has been done.  A final completion date has not yet been set, but is expected to be set at the next construction team meeting to be held next week.
 

 
 

           

           
(Click on a thumbnail to enlarge photo)

 
 
Links to Previous Updates

  Update 1 - 06-09-06       Update 5 - 10-03-06       Update 9   - 02-01-07      Update 12 - 05-01-07
  Update 2 - 07-01-06       Update 6 - 11-01-06       Update 10 - 03-01-07      Update 13 - 06-01-07
  Update 3 - 08-01-06       Update 7 - 12-04-06       Update 11 - 04-01-07      Update 14 - 07-01-07
  Update 4 - 09-01-06       Update 8 - 01-02-07

    

Construction
Drawings

Front Elevation

Rear Elevation

Lower Level Plan

Main Level Plan
Upper Level Plan

 


©1997-2008 White River Township Fire Department, Inc.  -  All rights reserved

White River Township Fire Department maintains this site ("the Site") for your personal entertainment, information, education, and communication.  Feel free to browse the Site, but please read the terms and conditions before doing so.