May 1, 2007
Station 51 construction update 12
|
The weather continues to hamper work at the new
fire station as persistent rains continue to soak the ground preventing the
installation of a permanent dual sump pit in the basement. Until the sump
pit is installed, work on the basement has been halted for fears of an
accidental flood should the existing pump fail. Additionally, delays
incurred with the water utility have also prevented some work from continuing.
Plumbing work has been put on hold until a permanent water supply can been
established and tested. Other work however has been continuing such as
painting, lightweight concrete floor installation, ceiling grids, bay floors,
and electrical fixtures. Some
photos of the past month's progress are displayed below.
|
Construction |
|
|
Front Elevation |
||
|
Rear Elevation |
||
|
Lower Level Plan |
||
![]() |
||
| Main Level Plan | ||
![]() |
||
| Upper Level Plan |
|
©1997-2008 White River Township Fire Department, Inc. - All rights reserved White River Township Fire Department maintains this site ("the Site") for your personal entertainment, information, education, and communication. Feel free to browse the Site, but please read the terms and conditions before doing so. |