March 1, 2007
Station 51 construction update 10
|
Weather continues to remain a factor out at the
Station 51 construction site as crews have been unable to work outside due to
the wet and extremely cold conditions.
Some interior progress is still being made though with drywall hanging and
finishing on the main and upper floors as well as the continuance of electrical,
HVAC, and plumbing trade work throughout. In the coming weeks, the bay
floor should be poured and bay doors should be hung soon after.
Additionally, the hookup of permanent utilities to the structure should be
complete.
|
Construction |
|
|
Front Elevation |
||
|
Rear Elevation |
||
|
Lower Level Plan |
||
![]() |
||
| Main Level Plan | ||
![]() |
||
| Upper Level Plan |
|
©1997-2011 White River Township Fire Department, Inc. - All rights reserved White River Township Fire Department maintains this site ("the Site") for your personal entertainment, information, education, and communication. Feel free to browse the Site, but please read the terms and conditions before doing so. |